Chilled Water Pipe Insulation Method Statement

1. Purpose

This method statement covers on site installation of thermal insulation for the complete chilled water piping system.

2. Scope

This procedure is applicable for insulation of all supply and return mains, headers, branches, risers, drips, run-outs, pump suction and discharge, pipework, fittings, flanges, valves, expansion and movement devices, flexible connections associated with the chilled water piping system installation .

3. Responsibilities

HVAC engineer and supervisor shall be responsible for implementation of this procedure and ensure the quality of insulation work is good.

Before starting the pipe insulation work you have to ensure that all chilled water piping have been installed and approved.

Pipe insulation method of statement

4. Insulation Method

  • Site supervisor to be issued with the latest revised construction drawings and signed-off pressure test certificates for the area by the construction department.
  • Site supervisor will requisition approved materials required for the specific installation to be carried out and adhere to the following guide lines.
  • Insulation Schedule.  Refer to latest revised construction drawing.
  • Supervisor to ensure that there is ample clearance around pipe fittings and plant to enable the installation of thermal insulation to be carried out.
  • Care is to be taken that surface sections of the installation to be insulated are free from damage, surfaces cleaned, painting has been completed, and is not wet or damp.
  • All joints will be wrapped with 150mm wide adhesive tape.
  • The Supervisor is to ensure that there are no insulation joints located within sleeves or at hangers.
  • Insulation of pipes passing through fire barriers are fire resistant and all gaps around will be sealed with fire resistant material.
  • Where sheathing is applied to insulation, the seams will be angled away from view whenever practical.
  • Sufficient adhesive shall be applied on the pipes and inside the insulation, the insulation will be wrapped to the pipe and pressed firmly at its location when the adhesive is ready for jointing of pipes surface and insulation.
  • Aluminium tape shall be used to make the insulation work cohesive and cover the gaps on joints etc.

5. Quality Control

It will be ensured that all completed insulation work is neat and tidy, and that there will be adequate spacing between pipes, valves and joints.  Generally, the clearance between pipework and or lagging will not be less than 200mm.  Where possible 125mm clearance will be left between the underside of the pipes and the finished floor level, and in no cases will this clearance be less than 100mm.  Suitable access for operation and maintenance of valves and other in line equipment will be ensured. The supervisor in charge and the QC officer will continuously monitor the activities to ensure that all components indicated on the approved drawings have been installed and that the installation is in accordance with the contract requirements and manufacturers recommendation.

Pipework Identification will be done as per the approved materials. All completed installation work will be protected to avoid damage until final inspection and sign off by the Client.

6. References

  • Insulation Check List.
  • Construction – System Drawings
  • Specification, Particular & General
  • Identification Procedure